Which of the following methods should the project manager select to investigate?
The schedule estimates for a particular work package that is underway were not properly
considered and the timescales are too tight. Which of the following methods should the project
manager select to investigate?
Which of the following is the MOST likely action the project manager should take?
A team member on a project uncovers a minor risk with the quality of a purchased component.
The team uses their combined expert judgment to determine that the risk to the deliverable is very
low. Which of the following is the MOST likely action the project manager should take?
Which of the following actions should the project manager undertake FIRST?
The change control board has requested that a project manager evaluate the impact of a major
change request that will affect the timetable of several work-packages. Which of the following
actions should the project manager undertake FIRST?
Which of the following would be the project managers BEST option?
A project manager has been engaged to deliver a project in South America and does not speak
Spanish. More than 50 percent of the project team will be Spanish speaking. Which of the
following would be the project managers BEST option?
Which of the following is the method for determining the critical path of a project?
Which of the following is the method for determining the critical path of a project?
which of the following documents should this have been previously addressed?
During handover stage a customer of a particular project noticed the extended warranty from a
particular vendor for a critical application has not been ordered. In which of the following
documents should this have been previously addressed?
which of the following performance statistics?
A variance between the planned scheduled work and the actual work completed would initially be
highlighted in which of the following performance statistics?
Which of the following is the correct progression of the project life cycle?
Which of the following is the correct progression of the project life cycle?
Which of the following would the project manager use to document the details of the project closure?
A project is cancelled unexpectedly prior to completion. Which of the following would the project
manager use to document the details of the project closure?
Which of the following is a representation of the difference between the planned costs of work completed compa
Which of the following is a representation of the difference between the planned costs of work
completed compared to the actual cost at a point in time?