A datacenter systems administrator needs to install a new server within an existing rack. Which of the following components would the systems administrator need to physic
ally install the server in the rack? (Choose two.)
A. Rail kit
B. Cable management
C. UPS
D. Network switch
E. Fiber cables
F. KVM