What adjustment to the project triangle components can you suggest to meet your customer’s needs?

Your customer scheduled a meeting to discuss a project you are managing. Early testing
indicates that there are currently quality problems with some of the more complex features.
The customer stated that quality and budget are his two main concerns: The project must
be developed within budget and must be very high quality. When you asked the customer if
he would be willing to extend the deadline to meet his objectives, he stated this was not
possible. What adjustment to the project triangle components can you suggest to meet your
customer’s needs?

PrepAway - Latest Free Exam Questions & Answers

A.
Suggest that the scope be limited to include only the most important features.

B.
Inform the customer that he must compromise one of the three elements of a project
triangle: quality, budget or schedule.

C.
Suggest that the customer hire temporary contractors.

D.
Suggest that the customer use a Gantt chart to add time to the project.