PrepAway - Latest Free Exam Questions & Answers

Which of the following is the best description of the d…

Which of the following is the best description of the develop project management plan
activity within the project-planning service component?

PrepAway - Latest Free Exam Questions & Answers

A.
Obtains customer surveys, captures lessons learned, and updates leading practices

B.
Integrates devices without disrupting the existing network or creating points of
vulnerability

C.
Documents planning of assumptions and decisions; facilitates communication among
stakeholders, and documents approved scope, cost, and schedule baselines

D.
Creates final network documentation that reflects “as-built” information for customer,
including specific design requirements and configurations


Leave a Reply