PrepAway - Latest Free Exam Questions & Answers

Which missing item should be your biggest concern?

A rollout plan from engineering has been sent to the NOC for review. The plan approves
deployment of a new router model at the customer premises for all new service activations. The
certification lab has fully tested the new router and found no issues. As a NOC engineer, you
review the plan for completeness. An item is missing from the plan to deploy the new routers.
Which missing item should be your biggest concern?

PrepAway - Latest Free Exam Questions & Answers

A.
product data sheet

B.
plan to replace existing customer premises routers with the new model

C.
listing of new syslog messages and SNMP traps

D.
environmental compliance statement


Leave a Reply