Which stories should the team include in Sprint 1, without splitting the stories?

An Agile team expects a velocity of 8. During sprint planning, the stories were estimatedand
prioritized in the following order:
Story A_4Story Points
Story B_2Story Points
Story C_3 Story Points
Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?

PrepAway - Latest Free Exam Questions & Answers

A.
Stories A, C, and D

B.
Stories A, B, and C

C.
Stories A, B, and D

D.
Stories B, C, and D