Which of the following must not performed in the project initiation process?

Which of the following must not performed in the project initiation process?

A.
Evaluate historical information

B.
List down business need

C.
List down stakeholders

D.
Create scope statement

Explanation:
Scope statement generally created in planning phase.
All others are done in initiation phase.