Define Activities is typically performed by which of the following:

Define Activities is typically performed by which of the following:

A.
Project Manager who created the WBS

B.
Management

C.
Project Team Members responsible for the work package

D.
Project Stakeholder

Explanation:
Define Activities is typically performed by Project Team Members. identify the activities that need to be done to complete the project.