A company is starting to introduce Agile practices, and the project manager has been asked
to identify how to introduce the new process. The project manager’s initial plan should be to:

A.
Institute daily standup meetings immediately.
B.
Communicate the Agile Manifesto to the team.
C.
Balance teaching principles with Agile practices.
D.
Rate the team’s progress in learning new methods.
really unsure. it would seem B perhaps
0
1
It should be A – daily standup meetings
0
1
D is an obvious incorrect answer, Both A and B are good answers, but C is the correct answer because it includes A and B
0
0
you cant institute daily stand up meets immediately. u would need the team to understnad the manifesto
0
0
i see your point however. C it is