What risk response is this?

You are the project manager of the YHG project for your company. Within the project, you and the
project team have identified a risk event that could have a financial impact on the project of
$450,000. This risk event has a 70 percent chance of occurring in the project. The project
identifies a solution that will reduce the probability of the risk event to ten percent, but it will cost
$260,000 to implement. Management agrees with the solution and asks that you include the risk
response in the project plan. What risk response is this?

What term is assigned to the low-level of stakeholder tolerance in this project?

[tagged]
You are the project manager of the NKJ Project for your company. The project’s success or failure
will have a significant impact on your organization’s profitability for the coming year. Management
has asked you to identify the risk events and communicate the event’s probability and impact as
early as possible in the project. Management wants to avoid risk events and needs to analyze the
cost-benefits of each risk event in this project. What term is assigned to the low-level of
stakeholder tolerance in this project?

What solution does the PMBOK recommend to reduce the influence of bias during qualitative risk analysis?

You are the project manager for your organization. You are working with your key stakeholders in
the qualitative risk analysis process. You understand that there is certain bias towards the risk
events in the project that you need to address, manage, and ideally reduce. What solution does
the PMBOK recommend to reduce the influence of bias during qualitative risk analysis?

What risk identification method could you use?

[tagged]
Your project spans the entire organization. You would like to assess the risk of the project but are
worried that some of the managers involved in the project could affect the outcome of any risk
identification meeting. Your worry is based on the fact that some employees would not want to
publicly identify risk events that could make their supervisors look bad. You would like a method
that would allow participants to anonymously identify risk events. What risk identification method
could you use?

What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identi

[tagged]
Frank is the project manager of the NHL Project for his company and he is starting the risk
identification process for the project. Frank needs to ensure that the correct stakeholders are
interviewed as part of risk identification. What document will help Frank to communicate and solicit
inputs of the project stakeholders during risk identification?