What is the status of the project whose data is shown in the following S-curve?
What is the status of the project whose data is shown in the following S-curve?
If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be th
If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?
Which of the following is a valid formula for calculating EAC?
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
Which of the following equations is used to calculate schedule variance?
Which of the following equations is used to calculate schedule variance?
Which tool and technique uses a statistical relationship between historical data and other variables to calcul
Which tool and technique uses a statistical relationship between historical data and other variables to calculate estimates?
Which of the following equations is used to calculate cost variance?
Which of the following equations is used to calculate cost variance?
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
CO = $7,000
CM = $10,500
CP = $11,000
What is the actual status of this project?
The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
Using the following data, what is the Schedule Performance Index (SPI)?
Using the following data, what is the Schedule Performance Index (SPI)?
EV = $500
PV= $750
AC= $1000
BAC= $1200
Which enterprise environmental factors are considered during cost estimating?
Which enterprise environmental factors are considered during cost estimating?