Which of the following information gathering techniques is described in the statement below?
[tagged]
Which of the following information gathering techniques is described in the statement below?
“Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment.”
Which of the following risk identification techniques is described in the statement below?
[tagged]
Which of the following risk identification techniques is described in the statement below?
“It is used to gather information where participants don’t know each other nor do they have to be present at the same location.”
What is a portfolio?
An organization supports both programs and projects for various industries. What is a portfolio?
what information to send back to the vendors?
[tagged]
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder’s conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?
Which of the following documents will help him for this?
[tagged]
Rick is a Program Manager for a large construction program. The program contains four projects.
Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?
What document defines how these things can be transferred from the program to the organization?
[tagged]
Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?
what action should be taken next?
[tagged]
A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?
which program process are you working on?
[tagged]
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program.
During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?
What is the cost performance index for this program?
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?
What duration compression technique should Kelly use in this instance?
[tagged]
Kelly’s program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They’ve asked Kelly to use a schedule duration compression technique that will help the program finish on time.
The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?