Which one of the following is NOT an input to the risk identification process?

[tagged]
You are the project manager of the GHY project for your organization. You are working with your
project team to begin identifying risks for the project. As part of your preparation for identifying the
risks within the project you will need eleven inputs for the process. Which one of the following is
NOT an input to the risk identification process?

Which one of the following statements best describes the requirements for the data type used in qualitative ri

You are the project manager of the CUL project in your organization. You and the project team are
assessing the risk events and creating a probability and impact matrix for the identified risks.
Which one of the following statements best describes the requirements for the data type used in
qualitative risk analysis?

Where will you record the mitigation response?

[tagged]
You are the project manager for your company and a new change request has been approved for
your project. This change request, however, has introduced several new risks to the project. You
have communicated these risk events and the project stakeholders understand the possible
effects these risks could have on your project. You elect to create a mitigation response for the
identified risk events. Where will you record the mitigation response?

which one?

[tagged]
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project
stakeholders have completed a round of qualitative risk analysis. He needs to update the risk
register with his findings so that he can communicate the risk results to the project stakeholders -including management. Mark will need to update all of the following information except for which
one?