PrepAway - Latest Free Exam Questions & Answers

Category: PgMP

Exam PgMP: Program Management Professional ( PgMP )

Which communication method is considered to be the best approach for this scenario?

[tagged]
Harriet is the program manager of a large program that has a high profile and visibility in her organization. Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

Is Eric’s organization liable to pay the ZAS Corporation for the work they have completed so far on the

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric’s organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric’s organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

This is an example of what?

[tagged]
Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike’s program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.
This is an example of what?

What principle should you share with these project managers that counterattack the concept of padding activiti

[tagged]
You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

What type of report can you create that will help you track your staff and their performance?

[tagged]
You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance?


Page 2 of 3012345...102030...Last »