What document defines how these things can be transferred from the program to the organization?
[tagged]
Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?
what action should be taken next?
[tagged]
A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?
which program process are you working on?
[tagged]
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program.
During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?
What is the cost performance index for this program?
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?
What duration compression technique should Kelly use in this instance?
[tagged]
Kelly’s program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They’ve asked Kelly to use a schedule duration compression technique that will help the program finish on time.
The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?
which type of performing is present in this scenario?
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time.
Based on this information which type of performing is present in this scenario?
Which one of the following is a likely reason why the project should be terminated?
Mary Anne is the program manager for her organization. In her program there are six projects.
One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated.
Which one of the following is a likely reason why the project should be terminated?
AOA refers to _____________.
AOA refers to _____________.
A contingency plan is ______________.
A contingency plan is ______________.
A unilateral contract under which the seller is paid a preset amount per unit of service is called _________.
A unilateral contract under which the seller is paid a preset amount per unit of service is called _________.