Which of the following information gathering techniques is described in the statement below?

[tagged]
Which of the following information gathering techniques is described in the statement below?
“Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment.”

what information to send back to the vendors?

[tagged]
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder’s conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Which of the following documents will help him for this?

[tagged]
Rick is a Program Manager for a large construction program. The program contains four projects.
Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?