Which of the following increases when one fast tracks the project?
Which of the following increases when one fast tracks the project?
Which of the following can be an effective tool during quality control to help determine the how the problem o
[tagged]
Which of the following can be an effective tool during quality control to help determine the how the problem occurred?
Which of the following terms is used for a schedule compression technique where two activities that were previ
[tagged]
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?
what process?
[tagged]
As a Program Manager, you decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?
Which of the following individual should respond to the risk with the preplanned risk response?
[tagged]
Which of the following individual should respond to the risk with the preplanned risk response?
Which of the following information gathering techniques is described in the statement below?
[tagged]
Which of the following information gathering techniques is described in the statement below?
“Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment.”
Which of the following risk identification techniques is described in the statement below?
[tagged]
Which of the following risk identification techniques is described in the statement below?
“It is used to gather information where participants don’t know each other nor do they have to be present at the same location.”
What is a portfolio?
An organization supports both programs and projects for various industries. What is a portfolio?
what information to send back to the vendors?
[tagged]
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder’s conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?
Which of the following documents will help him for this?
[tagged]
Rick is a Program Manager for a large construction program. The program contains four projects.
Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?