what is estimate at completion (EAC) for this program?
You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?
what other stakeholders are communicating about the project risk events?
[tagged]
You are the project manager of a large, high-profile project in your organization. You have realized
that politics within your company may affect the true identification of risk events within the project.
You decide that you’d like to use a method to identify risk events through an anonymous process.
Which one of the following risk events will allow you to collect and distribute risk information
without the stakeholders knowing what other stakeholders are communicating about the project
risk events?
What is the project’s schedule performance index?
You are the project manager of the NNH Project. In this project you have created a contingency
response that the schedule performance index should be less than 0.93. The NHH Project has a
budget at completion of $945,000 and is 45 percent complete though the project should be 49
percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.
What is the project’s schedule performance index?
what kind of document to show all of the program deliverables based on the program scope?
[tagged]
June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?
Which one of the following is the best explanation for completing qualitative risk analysis?
David is the project manager of HGF project for his company. David, the project team, and several
key stakeholders have completed risk identification and are ready to move into qualitative risk
analysis. Tracy, a project team member, does not understand why they need to complete
qualitative risk analysis. Which one of the following is the best explanation for completing
qualitative risk analysis?
which one?
[tagged]
A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
Which risk response can you choose that will also cause you to update the human resource management plan?
[tagged]
You work as a project manager for BlueWell Inc. Your project is running late and you must
respond to the risk. Which risk response can you choose that will also cause you to update the
human resource management plan?
what is the cost performance index (CPI) for this program?
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
which of the following processes?
[tagged]
The Project Risk Management knowledge area focuses on which of the following processes?
Each correct answer represents a complete solution. Choose all that apply.
what portion of a project are risk and opportunities greatest and require intense planning and anticipation of
In what portion of a project are risk and opportunities greatest and require intense planning and
anticipation of risk events?