PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

how many pennies is your program losing per dollar spent on the work?

You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?

What plan should Wanda reference and update to complete her team development process?

[tagged]
Wanda is the program manager for her organization. Her program team consists of resources from across the organization – many of whom have not worked together before. Wanda thinks that she’ll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?

What type of a response strategy is this?

[tagged]
Mary is the project manager of the HGH Project for her company. She and her project team have
agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG
Company to fulfill the order. The NBG Company can guarantee orders within three days, but the
costs of their products are significantly more expensive than the current vendor. What type of a
response strategy is this?