PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

what is the cost performance index (CPI) for Donna’s project?

Donna’s project has a budget at completion of $1,987,560 and she is currently 40 percent
complete. Her project schedule called for her to be 45 percent complete but there have been some
complications in the project. These complications have caused Donna to spend $125,000 more
than what the work she has completed is worth. Based on this information what is the cost
performance index (CPI) for Donna’s project?

What approach should Kenny use in the project?

Kenny is the project manager for the NHQ organization. She is creating the project duration
estimates. She has stressed to her project team that they will need to create accurate and reliable
project duration estimates without padding their estimates for errors or risks. Kenny is also relying

on historical information to help her predict the duration of the project work. Jennifer, one of the
project team members, wants to know how Kenny will account for the certain-to-happen errors and
delays in the project schedule. What approach should Kenny use in the project?

What type of forecasting method is management asking you to use?

You are the project manager for your organization. Your project is doing fine on time and cost, but
management wants to address the project performance for future accomplishment. Management
has asked you to begin reporting and forecasting your project’s health based on a moving
average, extrapolation, trend estimation, and growth curve. What type of forecasting method is
management asking you to use?


Page 392 of 512« First...102030...390391392393394...400410420...Last »