how many communication channels exist within this project?

Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and
she needs to express to her project team and to the management the importance of
communication in this project. She would like to show the number of stakeholder communication
channels in the project. Based on this information how many communication channels exist within
this project?

what is this project’s to-complete performance index?

You are the project manager of the GHY Project. This project is scheduled to last for one year and
has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are

supposed to be at your second milestone, which accounts for half of the project completion. There
have been some errors in the project, which has caused you to spend $2,073,654. Based on the
budget at completion, what is this project’s to-complete performance index?