What is this project’s schedule variance?

Allen works as a project manager of the NHY project. This project is scheduled to last for two
years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though
he is supposed to be at his second milestone, which accounts for half of the project completion.
There have been some errors in the project, which have caused Allen to spend $2,093,754. What
is this project’s schedule variance?