If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.
What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?
Which of the following will be required to perform simulation for schedule risk analysis?
Which of the following will be required to perform simulation for schedule risk analysis?
The risk register contains which of the following?
The risk register contains which of the following?
Which of the following is an input to identify risk?
Which of the following is an input to identify risk?
Which of the following is one of the tools and techniques for the Define Activities process?
Which of the following is one of the tools and techniques for the Define Activities process?
Which of the following is a tool and technique to develop the schedule?
Which of the following is a tool and technique to develop the schedule?
Rolling wave planning is used as a tool and a technique in which of the following processes?
Rolling wave planning is used as a tool and a technique in which of the following processes?
What is the critical path duration for the given schedule network?
Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships.
What is the critical path duration for the given schedule network?
What is the total float on path BEG?
Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships.
What is the total float on path BEG?