When should a performance baseline be captured?

A.
after the initial installation of the equipment, during normal daily operation
B.
after the initial installation of the equipment, during peak operating conditions
C.
before and after each step of the initial installation of the equipment
D.
three times a day during the first week following the initial installation of the equipment