Which potential issue be discussed the customer before proposing the HPE StoreVirtual solution?

You design and size an HPE StoreViriual solution for an SMB customer environment according to these
requirements
High availability between two data centers is needed
3 TB of data should be replicated
2×1 Gb/s links are needed between Sites A and B
A round trip time of 1.8 ms is needed between sites A and B
A third site, Site C, is needed for Failover Manager (F OM) connected with 100 MB/s
There is a latency of 55 ms between Site C and the other sites.

Which potential issue be discussed the customer before proposing the HPE StoreVirtual solution?