Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?
A. Phase E
B. Phase F
C. Phase G
D. Phase H
E. Requirements Management
2 Comments on “Which ADM phase establishes the connection between the architecture organization and the implementation organi”
seenagapesays:
C
0
0
Punjabsays:
I initially thought that phase F – opportunities and solutions were where you would be producing the architectural contract and G was just about governance (i.e. after contracts have been signed).
If you read the description of G from the spec, this is incorrect and phase G is about identifying resources and putting contracts in place:
1) Confirm scope and priorities for deployment with development management
2) Identify deployment resources and skills
3) Guide Development of Solutions deployment -> this is where the architecture contract is documented.
4) Perform Enterprise Architecture Compliance REviews
5) Implement Business and IT Operations
6) Perform post-Implementation Review and Close the Implementation.
C
0
0
I initially thought that phase F – opportunities and solutions were where you would be producing the architectural contract and G was just about governance (i.e. after contracts have been signed).
If you read the description of G from the spec, this is incorrect and phase G is about identifying resources and putting contracts in place:
1) Confirm scope and priorities for deployment with development management
2) Identify deployment resources and skills
3) Guide Development of Solutions deployment -> this is where the architecture contract is documented.
4) Perform Enterprise Architecture Compliance REviews
5) Implement Business and IT Operations
6) Perform post-Implementation Review and Close the Implementation.
Hence C is the correct answer.