Which of the following statements about the Project Initiation Documentation are true? 1.
The Project Initiation Documentation is used to ensure that a sound basis exists. 2. The
Project Initiation Documentation should be updated at the end of each stage to reflect the
current status of a project before the Project Board authorizes a project,
A.
Only 2 is true
B.
Both 1 and 2 are true
C.
Neither 1 or 2 are true
D.
Only 1 is true