What product records any time tolerances agreed between the Project Manager and Team Manager?

What product records any time tolerances agreed between the Project Manager and Team
Manager?

A.
Work Package

B.
Project Initiation Documentation

C.
Product Description

D.
Stage Plan

Explanation: