Which of the following can be ascertained by viewing this report?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
ABC.com is making use of Scrum as the process framework for new projects. You have opened
the Sprint Burndown report.

Which of the following can be ascertained by viewing this report? (Choose all that apply.)

PrepAway - Latest Free Exam Questions & Answers

A.
The speed at which your team has delivered backlog items.

B.
The amount of work that remains in a sprint backlog.

C.
The amount of work that the team must still perform to complete a product release.

D.
The speed at which your team has completed tasks.

E.
The amount of effort that your team has reported as complete for each sprint.

F.
When your team will achieve the goal or goals of the sprint.

G.
The amount of backlog effort that your team can handle in future sprints.

Explanation: