PrepAway - Latest Free Exam Questions & Answers

Which of the following actions should you take NEXT?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
ABC.com is making use of the Microsoft Visual Studio Scrum 2.0 process template to develop a
web application. Subsequent to the development team committing to supply a collection of Product

Backlog Item (PBI) work items for the impending sprint, you run the preliminary tests for the PBIs
in scope.
Since you are intending to include additional tests throughout the sprint, you have been instructed
to make sure that the additional tests are automatically added to your test plan.
You start by generating work items for the acceptance tests.
Which of the following actions should you take NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
You should consider connecting the test cases to the associated PBI work items.

B.
You should consider connecting the test cases to the test plan.

C.
You should consider adding the PBIs to the test plan.

D.
You should consider adding the PBIs to the test suite.

Explanation:


Leave a Reply