PrepAway - Latest Free Exam Questions & Answers

Which of the following actions should you take?

You work as a Project Manager at ABC.com. You are managing a project using Project Server 2010. You have been tasked with configuring a project resource so that the demand for the project is displayed by the work estimates. You have also been informed that your configurations should not have an effect on the availability of the resources. Which of the following actions should you take?

PrepAway - Latest Free Exam Questions & Answers

A.
You should use work resources without the Resource can be leveled option.

B.
You should use material resources with the Resource can be leveled option.

C.
You should make use of generic resources.

D.
You should use the disable Resource Leveling on all resources option.


Leave a Reply