Exam 74-343: Managing Projects with Microsoft Project 2013

You need to enter the hours in your Project Schedule on a weekly basis

You are a project manager who uses Project Professional 2013. You manage a software development
project and have baselined the project. Your Project Management Office (PMO) requires you to
capture the actual hours per resource for each task in your project schedule. You use these weekly
actual hours to generate a weekly report for your project sponsor. Your resources report their actual
hours each Friday. You need to enter the hours in your Project Schedule on a weekly basis. What
should you do?

You need to correct these values before re-entering the tracking data

You manage a project by using Project Professional 2013. Your project is updated with changes to
the baseline for selected tasks. You back up your project fife before you start your next tracking
cycle. After completing the tracking cycle, you notice that the baseline duration values on some of
the summary tasks are not correct. You need to correct these values before re-entering the tracking
data. You open the backed up version of the project schedule. What should you do next?