You need to update Baseline1 only for the two new tasks
You have added two new tasks to your project. Both tasks are subtasks to a summary task.
You need to update Baseline1 only for the two new tasks. What should you do?
Which two actions should you perform?
You use Project Professional 2010 to manage a software development project as shown in
the exhibit. (Click the Exhibit button.)
You need to cancel the Develop prototype based on functional specifications task. You also
need to retain all the information from the task. Which two actions should you perform?
(Each correct answer presents part of the solution. Choose two.)
What percentage of units should be reflected in the schedule by Adam’s workload?
DRAG DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to
the schedule as shown in the exhibit. (Click the Exhibit button.)
Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on
the first day and informed you that he needs an additional 9 hours of work to finish. You
update the schedule. What percentage of units should be reflected in the schedule by
Adam’s workload? (To answer, drag the appropriate units to the correct locations in the
answer area.)
You need to ensure that you can view only the tasks on your projects critical path
You need to ensure that you can view only the tasks on your projects critical path. What
should you do?
You need to find out the reason for the display of the icon
The red person icon is displayed next to one of your tasks. You need to find out the reason
for the display of the icon. What should you do?
Which set of values describes the task?
One of your tasks in your project plan is 50 percent complete. The task has a finish variance
of 4 days and a work variance of -14 days. Which set of values describes the task?
You need to identify the problem
You enter the finish date for a task, and then assign a resource. You discover that the task is
automatically scheduled for two weeks past the finish date you have entered. You need to
identify the problem. What should you do?
Which two actions should you perform?
Your project contains several baselines. By mistake, you save one of your baselines in
Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline
information. You also need to create a new Baseline5 by using today’s data. Which two
actions should you perform? (Each correct answer presents part of the solution. Choose
two.)
Which default view should you use?
You update your project schedule based on information received from your team members
in today’s status meeting. You need to compare the current revised project schedule with the
baseline schedule side by side. Which default view should you use?
You need to ensure that you can view critical tasks on all independent networks of tasks within the project
Your project contains many tasks that have dependencies and result in independent
networks of tasks. You need to ensure that you can view critical tasks on all independent
networks of tasks within the project. What should you do?