What percentage of units should be reflected in the schedule by Adam’s workload?

DRAG DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to
the schedule as shown in the exhibit. (Click the Exhibit button.)
Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on
the first day and informed you that he needs an additional 9 hours of work to finish. You
update the schedule. What percentage of units should be reflected in the schedule by
Adam’s workload? (To answer, drag the appropriate units to the correct locations in the
answer area.)