what is the most appropriate next test phase?

Topic 12, Scenario 12 “Automatic Teller Machine (ATM)”
You are a test manager in charge of integration, system and acceptance testing for a bank. You
are working on a project to upgrade an existing ATM to allow customers to obtain cash advances
from supported credit cards. The system should allow cash advances from €20 to €500,
inclusively, for all supported credit cards. The supported credit cards are American Express, VISA,
Eurocard and Mastercard.
In the master test plan the following items are listed in the section named “items and/or features to
be tested”:
I All supported credit cards
II Language localization
II Valid and invalid advances
IV Usability
V Response time
*****************************

Given is the following defect removal chart reported at the end of system testing – showing total
defects detected and closed defects (fixed and successfully retested). A number of open defects
are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance testing to verify the business process

B.
Acceptance testing to verify operational requirements

C.
Requirements testing as part of testing regulatory compliance

D.
Another system test cycle to verify defect resolution

Explanation: