Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in
the project planning processes is now coming into fruition. What individual should respond to the
risk with the preplanned risk response

PrepAway - Latest Free Exam Questions & Answers

A.
Project sponsor

B.
Risk owner

C.
Diane

D.
Subject matter expert