PrepAway - Latest Free Exam Questions & Answers

Which one of the following is a valid response to the identified risk event

Your project team has identified a project risk that must be responded to. The risk has been
recorded in the risk register and the project team has been discussing potential risk responses for
the risk event. The event is not likely to happen for several months but the probability of the event
is high. Which one of the following is a valid response to the identified risk event

PrepAway - Latest Free Exam Questions & Answers

A.
Earned value management

B.
Risk audit

C.
Corrective action

D.
Technical performance measurement