Where should she document the risks associated with this technology so she can track the risk status and respo

Adrian is a project manager for a new project using a technology that has recently been
released and there’s relatively little information about the technology. Initial testing of the
technology makes the use of it look promising, but there’s still uncertainty as to the longevity
and reliability of the technology. Adrian wants to consider the technology factors a risk for
her project. Where should she document the risks associated with this technology so she
can track the risk status and responses?

Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

You work as a project manager for TechSoft Inc. You are working with the project
stakeholders onthe qualitative risk analysis process in your project. You have used all the
tools to the qualitative risk analysis process in your project. Which of the following
techniques is NOT used as a tool in qualitative risk analysis process?

what type of risk response?

Tracy is the project manager of the NLT Project for her company. The NLT Project is
scheduled to last 14 months and has a budget at completion of $4,555,000. Tracy’s
organization will receive a bonus of $80,000 per day that the project is completed early up
to $800,000. Tracy realizes that there are several opportunities within the project to save on
time by crashing the project work. Crashing the project is what type of risk response?