Which business process diagram component will determine if incoming paths are active so that the process flow

Which business process diagram component will determine if incoming paths are active so
that the process flow does not wait for paths that will never complete?

PrepAway - Latest Free Exam Questions & Answers

A.
Subprocess

B.
Decision Service

C.
Parallel Gateway

D.
Inclusive Gateway