What must be performed first at the local data center?

A customer has a multi-target Three Data Center (3DC) implementation to protect a mission
critical UNIX application. The production host crashes, but the array and network are still
working. The customer wants to bring up the application on a host at the local data center
and still maintain two remote copies of the data. What must be performed first at the local
data center?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform swap takeover for the HUR pairs.

B.
Perform swap takeover for the TrueCopy pairs.

C.
Perform Delta Resync between the local and remote arrays.

D.
Perform Delta Resync between the local and production arrays.