What must be performed first at the local data center?

A customer has a cascaded Three Data Center (3DC) implementation to protect a mission
critical UNIX application. The production host crashes, but the array and network are still up.
The customer wants to bring up the application on a host at the local data center and still
maintain two remote copies of the data. What must be performed first at the local data
center?

PrepAway - Latest Free Exam Questions & Answers

A.
Suspend HUR pairs.

B.
Suspend TrueCopy pairs.

C.
Perform swap takeover for the HUR pairs.

D.
Perform swap takeover for the TrueCopy pairs.