PrepAway - Latest Free Exam Questions & Answers

What value (in days) should be used for planning?

During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?

PrepAway - Latest Free Exam Questions & Answers

A.
2

B.
5

C.
7

D.
8

Explanation:


Leave a Reply