The group that authorizes changes that must be installed faster than the normal process is called th

The group that authorizes changes that must be installed faster than the normal process is called the?

A.
CAB Emergency Committee (CAB/EC)

B.
Emergency CAB (ECAB)

C.
Urgent Change Board (UCB)

D.
Urgent Change Authority (UCA)