PrepAway - Latest Free Exam Questions & Answers

What is one of the necessary conditions before an MSC cycle switch is performed at Site B?


A composite group spanning two Symmetrix arrays is set up to run SRDF/Star using Cascaded SRDF as shown in the exhibit.
What is one of the necessary conditions before an MSC cycle switch is performed at Site B?

PrepAway - Latest Free Exam Questions & Answers

A.
Transmission of delta sets from Site B to Site C has finished

B.
SDDF bitmaps have been swapped at Site A

C.
Invalid track count between Sites A and C must be under 30000

D.
SYMCLI_STAR_ALLOW_CASCADED_CONFIGURATION option must be enabled in the option file