EMC Exam Questions

What do you recommend?

You are designing a new disaster recovery solution with VMAX arrays. During the initial project
kick-off meeting, the customer reports their environment can tolerate five minutes or less of data
recovery following a disaster but have not yet determined the maximum allowable downtime for
their applications.
The customer asks which remote replication methods you recommend for their environment.
What do you recommend?

A.
Defer making a recommendation until the application RTO is known.

B.
Recommend the disaster recovery solution as described in the Sales Order.

C.
Defer making a recommendation until the application RPO in known.

D.
Recommend the disaster recovery solution described in the Statement of Work.