You are designing a new disaster recovery solution with VMAX arrays. During the initial project
kick-off meeting, the customer reports their environment can tolerate five minutes or less of data
recovery following a disaster but have not yet determined the maximum allowable downtime for
their applications.
The customer asks which remote replication methods you recommend for their environment.
What do you recommend?

PrepAway - Latest Free Exam Questions & Answers

A.
Defer making a recommendation until the application RTO is known.

B.
Recommend the disaster recovery solution as described in the Sales Order.

C.
Defer making a recommendation until the application RPO in known.

D.
Recommend the disaster recovery solution described in the Statement of Work.