Which factor was not included in the pre-installation planning?

After a pre-installation walkthrough, the server technician concludes that the power outlets, rack dimensions, physical security, and network cabling are all acceptable. However, one factor is missing in the pre-installation planning, so the technician decides not to install the server in this location.

Which factor was not included in the pre-installation planning?

PrepAway - Latest Free Exam Questions & Answers

A.
location

B.
electrostatic discharge

C.
wall materials

D.
environment