Which of the following is a key aspect of the Agile project management methodol
ogy?
A. Test-driven
B. Daily standup meetings
C. Short project durations
D. Defined list of requirements
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286