Which of the following documents should be used to provide high-level repor
ting to key stakeholders?
A. Dashboard
B. Communication plan
C. Statement of work
D. Project charter
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325