Which activity is associated with the task of identifying project parameters and matrices, such as critical success factors, project objectives, cost controls, timeframes, and commitments within the plan phase of the Deployment Project Management service component?

PrepAway - Latest Free Exam Questions & Answers

A.
Conduct project kickoff workshops.

B.
Develop the work breakdown structure.

C.
Produce a master project plan.

D.
Perform project control and monitoring.

E.
Develop a project management plan.