PrepAway - Latest Free Exam Questions & Answers

, which activity is associated with the task of proposing and gaining agreement

In the Deployment Project Management service component within the plan phase, which activity is associated with the task of proposing and gaining agreement on a governance model that will be used to communicate to key stakeholders and business owners?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform project control and monitoring.

B.
Conduct project kickoff workshops.

C.
Develop the work breakdown structure.

D.
Develop a project management plan.

E.
Produce a master project plan.


Leave a Reply