Which two steps will accomplish this task?

You are configuring an FCIP tunnel with four circuits. Two of the circuits will be active and
the other two will be in standby in case of failure. You want to ensure that there are always
at least two active circuits in the event of a failure.Which two steps will accomplish this task?
(Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Configure all the circuits as metric 1.

B.
Configure two circuits as metric 1 and two circuits as metric 0.

C.
Configure two failover groups consisting of a metric 1 and a metric 0 circuit per group.

D.
Configure two failover groups consisting of two metric 1 circuits in one group and two
metric 0 circuits in the second group.